Conveyance

Lake June Phase 1 – Pump Station

June Lake Phase 1 – Pump Station Spring Hill, Tennessee  June Lake is a premiere mixed-use development located on nearly 800-acres at the gateway to the City of Spring Hill, Tennessee. Located adjacent to I-65, June Lake is fully entitled for 2,900 homes, 3.9 million SF of commercial office space, 1.3 million SF of retail and restaurant space, and 400 hotel rooms. DCCM was contracted to design and permit the water and sewer infrastructure for the development, including the Phase 1 sanitary sewer lift station. The lift station was designed to manage a peak demand of 604 gpm, with a total dynamic head (TDH) of 70.2 ft. The design was complicated by the force main having to overcome two separate high points. Ultimately, a steady-state analysis determined that the water column within the force main would start to separate at Station 14+00 and become gravity flow at Station 14+40. The lift station has a 10-ft diameter wet well and utilizes duplex 50-horsepower suction-lift Gorman-Rupp pumps. The station is equipped with an emergency bypass quick-connect fitting and valving that allows City maintenance equipment to continue to manage the demand if the pumps are offline. Services included survey, engineering design, permitting, and construction administration. At a Glance $85,000 Design Cost Markets Water Surveying Services Water & Wastewater Surveying

24-inch Putah South Canal Emergency Raw Water Repair

24-inch Putah South Canal Emergency Raw Water Repair Benicia, CA DCCM provided construction management and full-time inspection services for the City of Benicia’s 24-inch Putah South Canal Emergency Raw Water Repair Project. The emergency repair addressed a critical raw water transmission line extending from private property near Watt Court, beneath Interstate 80, and into City of Fairfield property. Due to the pipeline’s importance and its location within a major transportation corridor, the project required accelerated construction, careful coordination, and strict traffic control and safety oversight. Construction activities included traffic control along the westbound shoulder of Interstate 80, excavation of entry and exit pits, slip lining of an 18-inch fusible PVC pipe, hydrostatic testing, and full site restoration. DCCM supported the City throughout all phases of construction, providing daily field inspection, documentation, safety compliance monitoring, and traffic control oversight to ensure work conformed to project plans, specifications, and regulatory requirements.  Construction management services included coordination with City staff, the contractor, property owners, and the design team; administration of submittals, RFIs, and change orders; cost and schedule monitoring; and preparation of progress reports and pay estimate recommendations. DCCM also supported project closeout by verifying punch list completion, reviewing record drawings, and delivering complete construction documentation. The project was successfully completed under emergency conditions while maintaining safety, quality, and schedule objectives.  At a Glance $97,000 Project Cost Markets Water Services Transportation Water & Wastewater

IH 45 and SH 6 Water Distribution System Improvements

IH 45 and SH 6 Water Distribution System Improvements Galveston County, Texas DCCM provided preliminary and final design and construction-phase services for 8,100 linear feet of 24-inch water line as part of a collaboration between the Galveston County Water Authority and Galveston County to provide potable water to a future residential area in Texas City. To accommodate this needed water line, an alignment was established at the intersection of Avenue L and a Galveston County Water Authority canal in Santa Fe, where the line connected to an existing water line and then extended along the north high bank of the canal to a metering station site west of IH 45. This project was funded by the State of Texas through a Community Development Block Grant and administered by the Texas General Land Office due to damage from Hurricane Ike. The funding was allocated to Galveston County, thereby funding the construction and managing the design and construction phases. At a Glance 8,100 Linear Feet 24-inch Water Line $1.8 million Csontruction Cost Markets Municipal Services Utilities Water & Wastewater

Countryside Wastewater Treatment Plant Decommission, Lift Station and Force Main Upgrade

Countryside Wastewater Treatment Plant Decommission, Lift Station and Force Main Upgrade League City, Texas DCCM was selected to provide preliminary engineering, final design, and construction services to decommission the existing Countryside Wastewater Treatment Plant (WWTP) and install a new lift station and new force main to divert wastewater to the existing Southwest Water Reclamation Facility. The existing lift station was decommissioned and replaced with a new 10-foot lift station featuring three 20-horsepower submersible pumps, providing a firm capacity of 850 gallons per minute for diversion service. The design included modifications to the existing sewer collection system, including the addition of new manholes and gravity lines to intercept and divert sewer flow to the new lift station. Construction sequencing, bypass pumping, and coordination were carefully planned to allow the construction of the new lift station, sewer diversion, and demolition of the existing lift station and wastewater treatment facilities. The new lift station featured a programmable logic controller (PLC)-based pump control panel, supervisory control and data acquisition (SCADA) access via a wireless antenna for remote monitoring, and a manual transfer switch to facilitate emergency generator connection in accordance with TCEQ requirements. At a Glance 850 Gallons per Minute $1.6 million Construction Cost Markets Municipal Services Water & Wastewater

108-Inch Northeast Transmission Line, Contract 99D-2

108-Inch Northeast Transmission Line, Contract 99D-2 Houston, Texas DCCM provided final engineering design and construction-phase services for 1.4 miles of 108-inch water main from Aldine Westfield Road to Willis Street in north Houston. This project was extremely complex due to the size of the water main and the congested area where the alignment was located. DCCM worked with the City of Houston and its Program Manager to develop a 50-foot water line easement through an existing urban region. To develop the preferred alignment, DCCM considered construction issues, including laydown areas, environmental constraints, traffic impacts, and existing utilities. DCCM developed alignment alternatives, such as tunnels instead of open-cut construction, in multiple areas to minimize or eliminate significant impacts on existing businesses, as numerous commercial buildings are close to the route. Tunnels were designed to mitigate the impact on the buildings and their operations in these areas. Since the project was in an urban region, DCCM worked closely with the existing utilities to develop utility conflict documents and support their relocation. The design also included construction phasing and traffic control to maintain access to residences, facilities, and emergency services. The water line was a significant transmission main constructed via open-cut and tunneling methods. Each method was optimized for the project. At a Glance 108-inch Water Main 7,400 Linear Feet $31 million Construction Cost Markets Municipal Surveying Services Water & Wastewater Surveying Utilities

42-inch Water Line Design, Segment 3 A1

42-inch Water Line Design, Segment 3 A1 Harris County, Texas DCCM provided final design and construction phase services for 14,000 linear feet of 42-inch water transmission line within a CenterPoint Energy electric transmission line corridor and easement. This water line is part of the West Harris County Regional Water Authority’s (WHCRWA) 2025 system, which will meet at least 60% of water demand with surface water. This is the latest project in a long history of working with WHCRWA to supply their surface water requirements. The project involved installing water lines in CenterPoint Energy’s electrical transmission line corridor for miles. Trenchless construction was required within 20 feet of truss towers and across busy roadways. Close coordination was maintained with the City of Houston and Harris County for permitting and the acquisition of record drawings. Collaboration with the design engineer ensured a proper connection to an 84-inch water line. Additionally, coordination with multiple petroleum pipelines and dry utilities in CenterPoint Energy’s corridor was necessary. At a Glance 42-inch Water Transmission Line $8.9 million Construction Cost Markets Municipal Surveying Services Water & Wastewater Program Management Surveying Utilities

Wheatland Wastewater Improvements

Wheatland Wastewater Improvements Wheatland, IN DCCM led an internal and external team of engineers to design and develop a new sanitary sewer system for the Town of Wheatland. This system included designing three positive displacement blowers for a new extended aeration plant along with several miles of new low pressure force main, one lift station, and a package wastewater treatment plant for the town of 500 people. The team evaluated wastewater lagoons for Wheatland being crucial for maintaining compliance with regulations and ensuring effective treatment. One of the key challenges in the design of project was ensuring the project met the Town’s limited budget, supported by a $14M SRF grant award for water/wastewater. Through a combination of creative design and funding solutions and selection of a minimally invasive technology such as low pressure sewer, DCCM was able to secure reasonable bids that allowed the project to proceed. At a Glance 10 Miles $10.2M Project Cost “The team (DCCM) is nothing short of amazing on the projects we have worked on with them. They are always organized and available if there are questions. I have seen Aaron Crow, Poject Manager, work along with his team members as he is always clear and concise on what he is asking for. I believe the team excels under his leadership and never feel overwhelmed or worried about the projects because they communicate with us to keep everyone organized and on task. They have definitely been an asset to our Town and Utility!” Erika Goble Wheatland Deputy Clerk Markets Municipal Water Services water Conveyance Treatment Water Resources

Scroll to Top