Treatment

Northeast Water Purification Plant Expansion

Northeast Water Purification Plant Expansion Houston, Texas DCCM partnered with the Houston Waterworks Team to perform a progressive design-build project to expand the existing City of Houston Northeast Water Purification Plant from 80 million gallons per day to 400 million gallons per day treatment capacity. DCCM was responsible for the structural and mechanical design of the new raw water intake pump station, located 1,000 feet offshore in the middle of Lake Houston. It has an access bridge and pump station platform with ten 1,000-horsepower vertical turbine pumps capable of delivering up to 560 million gallons per day (ultimate capacity) of raw water from Lake Houston to the Northeast Water Purification Plant. DCCM performed structural design modeling and simulation of a 30,000-square-foot pump station platform that supported the pump facility building, pump equipment, piping and electrical switchgears, and process mechanical design to install ten 1,000-horsepower vertical turbine pumps with two 96-inch header pipes, control valves, and a 25-ton bridge crane. The intake pump station platform is 13 feet above normal water level and 250 feet long by 120 feet wide, supported on a cast-in-place 1-foot-thick concrete deck with 3.5-foot-deep grade beams. DCCM designed and analyzed the intake pump station using the finite element program Structural Analysis and Designing Program. Dynamic analyses were also performed to verify the platform’s dynamic behavior under pump dynamic loads during operation. Bentley 3D models were used in the final design by structural, architectural, process mechanical, piping, plumbing, instrumentation, and electrical design disciplines. All design models were integrated to detect conflicts and complete the final product. At a Glance 400 million Gallons per Day $165 million Construction Cost Markets Municipal Services Water & Wastewater Utilities

Countryside Wastewater Treatment Plant Decommission, Lift Station and Force Main Upgrade

Countryside Wastewater Treatment Plant Decommission, Lift Station and Force Main Upgrade League City, Texas DCCM was selected to provide preliminary engineering, final design, and construction services to decommission the existing Countryside Wastewater Treatment Plant (WWTP) and install a new lift station and new force main to divert wastewater to the existing Southwest Water Reclamation Facility. The existing lift station was decommissioned and replaced with a new 10-foot lift station featuring three 20-horsepower submersible pumps, providing a firm capacity of 850 gallons per minute for diversion service. The design included modifications to the existing sewer collection system, including the addition of new manholes and gravity lines to intercept and divert sewer flow to the new lift station. Construction sequencing, bypass pumping, and coordination were carefully planned to allow the construction of the new lift station, sewer diversion, and demolition of the existing lift station and wastewater treatment facilities. The new lift station featured a programmable logic controller (PLC)-based pump control panel, supervisory control and data acquisition (SCADA) access via a wireless antenna for remote monitoring, and a manual transfer switch to facilitate emergency generator connection in accordance with TCEQ requirements. At a Glance 850 Gallons per Minute $1.6 million Construction Cost Markets Municipal Services Water & Wastewater

69th Street Wastewater Treatment Plant, Packages 5 and 6

69th Street Wastewater Treatment Plant, Packages 5 and 6 Houston, Texas Package 5: DCCM completed field investigation and final design services to replace the existing 69th Street wastewater treatment process instrumentation and controls for the entire wastewater facility. Work included the replacement of flow meters, analyzers, pressure and level instruments, pneumatic and electrical control valves, electrical conduits, and control panels for the lift station, headworks, flow distribution controls, oxygen reactors, clarifiers, return activated sludge and waste activated sludge pump stations, sludge thickeners, and an odor control system. Package 6: DCCM provided a preliminary engineering study, including filter pilot testing and evaluation of new tertiary filter technology to replace the existing sand filters at the 69th Street WWTP. DCCM worked with the City of Houston to procure a new filter system. The final design included modifying the existing treatment facility infrastructure and adjusting the hydraulic profile to fit the new filter system, a new electrical system with instrumentation, and control systems. The existing sand filter system was demolished and replaced with a Kruger disc filter system. The new disc filter system is rated for an average of 220 million gallons per day and a peak flow of 440 million gallons per day, making it Texas’s largest tertiary filter system installation. At a Glance 440 million Gallons Per Day $25.4 million Construction Cost Markets Municipal Services Water & Wastewater

Wheatland Wastewater Improvements

Wheatland Wastewater Improvements Wheatland, IN DCCM led an internal and external team of engineers to design and develop a new sanitary sewer system for the Town of Wheatland. This system included designing three positive displacement blowers for a new extended aeration plant along with several miles of new low pressure force main, one lift station, and a package wastewater treatment plant for the town of 500 people. The team evaluated wastewater lagoons for Wheatland being crucial for maintaining compliance with regulations and ensuring effective treatment. One of the key challenges in the design of project was ensuring the project met the Town’s limited budget, supported by a $14M SRF grant award for water/wastewater. Through a combination of creative design and funding solutions and selection of a minimally invasive technology such as low pressure sewer, DCCM was able to secure reasonable bids that allowed the project to proceed. At a Glance 10 Miles $10.2M Project Cost “The team (DCCM) is nothing short of amazing on the projects we have worked on with them. They are always organized and available if there are questions. I have seen Aaron Crow, Poject Manager, work along with his team members as he is always clear and concise on what he is asking for. I believe the team excels under his leadership and never feel overwhelmed or worried about the projects because they communicate with us to keep everyone organized and on task. They have definitely been an asset to our Town and Utility!” Erika Goble Wheatland Deputy Clerk Markets Municipal Water Services water Conveyance Treatment Water Resources

Verdera North Water Infrastructure Project

Verdera North Water Infrastructure Project

Verdera North Water Infrastructure Project Lincoln, CA The project provides the City with adequate drinking water supply and storage to enhance the resiliency of the water supply system and accommodate growth. Together these improvements provide the northern areas of Lincoln with safe and reliable drinking water. In addition, the metering station and 42-inch pipeline will also be used to serve a large portion of western Placer County when Placer County Water Agency’s future Ophir Water Treatment Plant and 60-inch pipeline is connected to the metering station. DCCM provided program management, project management and design oversite services from inception through construction including developing project budgets, consultant selection (engineering and CM), preliminary design studies, environmental processing, project approvals, design oversight, bidding and award, SCADA, construction, and start-up. The major elements of this $25M project included:  1.3-miles of 42-inch CMLC steel pipeline 4,500sf pressure reducing/metering station 5-MG pre-stressed concrete tank 0.9-miles of 36-inch ductile iron pipe  933-feet of 16-inch PVC pipeline to high elevation customers  Decommissioning a 7-acre municipal water storage pond Pad and yard piping for a future 5-MG tank Extensive oak tree mitigation planning Recreational trail around the project site At a Glance APWA Sacramento, CA Project of the Year “Environment (Water)” Award $25M Project Cost Markets Water Municipal Services Program Management Water

Scroll to Top