Utility Coordination

2020 Multi-Street Reconstruction

2020 Multi-Street Reconstruction Pasadena, Texas DCCM provided preliminary and final design, bidding, and construction-phase services for reconstructing 12,220 linear feet of neighborhood residential streets and a collector street within the City of Pasadena. The project comprised nine separate residential streets, including West Park Lane, Madison Avenue, Austin Avenue, Easthaven Drive, Magnolia Street, Tilden Drive, Polk Avenue, Kansas Street, and Llano Street, a major collector.  The project scope included the complete reconstruction of existing neighborhood concrete roads, including storm sewer, sanitary sewer, and water line replacements and upgrades. The project also included Americans with Disabilities Act (ADA)-compliant sidewalks/shared-use paths and ramps, signing and pavement markings, traffic control, a stormwater pollution prevention plan (SWPPP), a complete drainage study, and a geotechnical report. This reconstruction project was bid on a unit-price basis before design began and executed on a fast-track schedule. This included close coordination between DCCM and the contractor during the design and continuous coordination with the City of Pasadena and the contractor. This close coordination allowed changes to be quickly made in the field during construction as required. Portions of the project required innovative engineering to provide the necessary detention within the street’s limits. This fast-track process will set the path for future projects designed and constructed within the City of Pasadena. The design and reconstruction of all streets were completed within an accelerated 12-month schedule. At a Glance 12,220 Linear Feet $11.4 million Construction Cost Markets Municipal Surveying Transportation Services Surveying Transportation Utilities Water & Wastewater

108-Inch Northeast Transmission Line, Contract 99D-2

108-Inch Northeast Transmission Line, Contract 99D-2 Houston, Texas DCCM provided final engineering design and construction-phase services for 1.4 miles of 108-inch water main from Aldine Westfield Road to Willis Street in north Houston. This project was extremely complex due to the size of the water main and the congested area where the alignment was located. DCCM worked with the City of Houston and its Program Manager to develop a 50-foot water line easement through an existing urban region. To develop the preferred alignment, DCCM considered construction issues, including laydown areas, environmental constraints, traffic impacts, and existing utilities. DCCM developed alignment alternatives, such as tunnels instead of open-cut construction, in multiple areas to minimize or eliminate significant impacts on existing businesses, as numerous commercial buildings are close to the route. Tunnels were designed to mitigate the impact on the buildings and their operations in these areas. Since the project was in an urban region, DCCM worked closely with the existing utilities to develop utility conflict documents and support their relocation. The design also included construction phasing and traffic control to maintain access to residences, facilities, and emergency services. The water line was a significant transmission main constructed via open-cut and tunneling methods. Each method was optimized for the project. At a Glance 108-inch Water Main 7,400 Linear Feet $31 million Construction Cost Markets Municipal Surveying Services Water & Wastewater Surveying Utilities

42-inch Water Line Design, Segment 3 A1

42-inch Water Line Design, Segment 3 A1 Harris County, Texas DCCM provided final design and construction phase services for 14,000 linear feet of 42-inch water transmission line within a CenterPoint Energy electric transmission line corridor and easement. This water line is part of the West Harris County Regional Water Authority’s (WHCRWA) 2025 system, which will meet at least 60% of water demand with surface water. This is the latest project in a long history of working with WHCRWA to supply their surface water requirements. The project involved installing water lines in CenterPoint Energy’s electrical transmission line corridor for miles. Trenchless construction was required within 20 feet of truss towers and across busy roadways. Close coordination was maintained with the City of Houston and Harris County for permitting and the acquisition of record drawings. Collaboration with the design engineer ensured a proper connection to an 84-inch water line. Additionally, coordination with multiple petroleum pipelines and dry utilities in CenterPoint Energy’s corridor was necessary. At a Glance 42-inch Water Transmission Line $8.9 million Construction Cost Markets Municipal Surveying Services Water & Wastewater Program Management Surveying Utilities

US 79 Widening

US 79 Widening Jewett, Texas The DCCM team designed a 10-mile schematic and environmental project in Leon County. The project consisted of widening US 79 from a two-lane section to a four-lane divided section from west of Jewett at FM 1512 to Buffalo. This project developed three alternatives and refined the preferred alternative based on stakeholder input from two public meetings, environmental constraints, and limited right-of-way (ROW). The team worked on developing all environmental technical reports required to obtain environmental clearance for ROW acquisition and utility relocation before the final design. One project challenge involved reintroducing a relief route around the City of Jewett during the 90% schematic design. The DCCM team collaborated with the Emerging Technologies group to devise potential relief routes and create exhibits for the upcoming public meeting. Additionally, the DCCM team generated 3D renderings for downtown design options and collaborated with the City of Jewett to gain consensus from key stakeholders. Another challenge involved two grade-separated railroad crossings with BNSF and UPRR. The UPRR crossing featured a rail siding to the Nucor Corporation plant. To address this, seven alternatives were developed to convert the Nucor Corporation at-grade crossing into a grade-separated crossing, ensuring access to Nucor Corporation plants and CR 347. In coordination with Nucor Corporation and TxDOT, the team worked to find a design solution that accommodated all parties while minimizing interchange construction costs. At a Glance 10 Miles $178 million Construction Cost Markets Transportation Services Transportation Utilities

Aerial view looking straight down at a multilane highway with a new crosswalk intersecting both directions of travel lanes

FM 2818 (Harvey Mitchell Parkway) Improvements

FM 2818 (Harvey Mitchell Parkway) Improvements College Station, Texas The FM 2818 (Harvey Mitchell Parkway) project in College Station is a story of innovation, collaboration, and technical excellence. DCCM led the team that worked closely with the City of College Station, TxDOT, Texas A&M University, and Easterwood Airport to address the region’s rapid growth and evolving transportation needs. Our journey began with a comprehensive corridor study and traffic analysis, which revealed that traditional intersection designs would not provide the necessary capacity or operational improvements. In response, we expanded our analysis to include six additional alternatives and ultimately selected an innovative “superstreet” (Restricted Crossing U-turn) design. This approach reduced signal phases at intersections, improved traffic flow, and provided flexibility for future upgrades to a controlled access facility. Our scope included data collection, accident and traffic analysis, environmental documentation, public involvement, identification of right-of-way (ROW) and easements, utility coordination, and topographic surveying. We also managed a team of eight subconsultants for specialized analyses and design tasks. We completed both the schematic and PS&E phases for FM 2818, developing a geometric design schematic from Wellborn Road to F&B Road, and seamlessly transitioning into detailed construction documents. The final schematic design was coordinated with the parallel PS&E design team, enabling construction documents to reach 60% design before schematic finalization. This efficient transition was made possible by keeping most of the same key staff and maintaining a strong project management plan throughout both phases. One of the most significant challenges was the presence of a major underground electric duct bank that conflicted with the proposed curb line and storm sewers. By conducting precise SUE QL-A potholing and collaborating with the city and TxDOT, we developed a solution that allowed the duct bank to remain in place while relocating the storm sewer, avoiding major disruptions and keeping the project on schedule. Another challenge arose when a new overpass at Jones-Butler Road was added late in the design process. Our team quickly adapted, revising schedules and resources to incorporate the new structure without impacting the letting date. Environmental considerations were also paramount. White Creek, which runs parallel to the corridor, required careful coordination to minimize impacts to the floodplain and wetlands. Through detailed grading, innovative barrier design, and close collaboration with regulatory agencies, we kept wetland impacts below permitting thresholds and avoided additional ROW acquisition. The FM 2818 project is now under construction. The result is a safer, more efficient, and future-ready corridor that supports the continued growth of College Station and the surrounding community. Traffic Analysis/Corridor Study Services DCCM performed a corridor study for FM 2818 from George Bush Drive to Wellborn Road. The study examined various alternatives, including many different intersection configurations. Ultimately, the conventional intersection designs failed to provide adequate operations. As a result, the superstreet concept was proposed and evaluated as a potential solution for the corridor. This provided the opportunity to reduce signal phases at intersections while maintaining the flexibility to upgrade the corridor to a controlled-access facility in the future should the need arise. Responsiveness: The original scope included an analysis of three options for access management along the corridor, none of which provided adequate capacity. To keep the project on schedule, the DCCM team worked with the City of College Station and TxDOT to identify and analyze six more options before the change order was processed. The innovative intersection used in the final design was one of these six additional options. Surveying Services During the S&E phase, DCCM provided a comprehensive topographic survey on this City of College Station/TxDOT street design project. The route was a 1.8-mile section of the existing state highway roadway. The extra width of the ROW created an unusually large, 80-acre project area, with several acres of native trees and brush. Using baseline survey points and information from the early 1970s, the ROW lines were accurately fitted to the topographic survey. Additionally, Baseline | DCCM had surveyed utility easements along the highway over 15 years prior, before any of the adjoining apartment complexes were developed. Schematic Design Services DCCM developed a geometric design schematic for FM 2818 from Wellborn Road to George Bush Drive. The project scope included conceptual and schematic design, data collection, accident and traffic analysis, conceptual design, schematic design, environmental documentation, public involvement, ROW/easement identification, utility coordination, project management, and topographic surveying. The initial scope included analyzing three design-year alternatives, developing a conceptual schematic for each, and developing the selected alternative through schematic design. Based on the results of the traffic analysis/conceptual design and meetings with City of College Station and TxDOT staff, it was determined that the three design-year alternatives would not adequately address growth issues along the project corridor; therefore, six additional alternatives were analyzed. Based on the traffic analysis and input from the City and TxDOT, a “super street” option was selected and developed through schematic design. SUE Services Under the SUE department’s TxDOT contract, the Bryan District requested that SUE QL-B designation be performed for their 3.2-mile FM 2818 Improvement project. More than 265,000 linear feet of utilities were identified on the project, resulting in a utility map that revealed numerous critical conflicts with the proposed roadway improvements. The designers and utility coordinators asked for 24 SUE QL-A test holes. All test holes were completed, the SUE QL-B designation and the conflicts it revealed were validated, and the designation was assigned. An additional SUE QL-B was requested for the downside streets to fully understand the utility impact. This project faced challenges, including complex traffic control and Texas A&M mowing the TxDOT ROW before each home football game. It was critical to complete the survey work each week before the Friday afternoon mowers arrived. At a Glance 40% Reduction in Corridor Travel Times $57.6 million Construction Cost Markets Transportation Environmental Services Transportation Surveying Utilities

SH 249 (Tomball Tollway), Phases I and II

SH 249 (Tomball Tollway), Phases I and II Tomball and Montgomery County, Texas DCCM was contracted by the Harris County Toll Road Authority (HCTRA) as the Program Management Consultant (PMC) for the design and management of both preliminary and final project designs, as well as construction management and inspection services for Phase II. We developed a project feasibility assessment, which resulted in the SH 249 (Tomball Tollway), Phases I and II engineering feasibility report, and served as the basis for the final design. On its first day of operation, eager toll users doubled the projected 17,000 daily toll transactions, cutting traffic on the existing frontage road in half. Funded entirely with toll road revenue paid by drivers who choose to use the Harris County toll road system, the final construction will extend the toll road into Montgomery and Grimes Counties to SH 105, streamlining trips to and from rapidly growing Grimes County and College Station. Phase I: Spring Cypress Road to FM 2920 This project provided travelers with four main lanes in each direction and was constructed between the existing TxDOT northbound and southbound non-tolled frontage roads. As PMC for HCTRA, DCCM completed an aggressive 9-month design program to deliver plans, specifications, and estimates (PS&E) for HCTRA to bid and construct this phase. DCCM provided leadership, schedule adherence, quality assurance, and oversight to 17 consultants, completing the PS&E for four new toll lanes in each direction along a 6-mile stretch of SH 249, adding five new bridges, retaining walls, and a drainage system that mitigates flooding. Drivers may now bypass seven stoplights while the frontage roads remain toll-free. All milestone submittals were met on time, and the project was constructed in only 16 months and under three construction contracts. Phase I was open to traffic in April 2015 and is exceeding all revenue forecasts.  Phase II: FM 2920 to Spring Creek (Harris/Montgomery County line) Design preparations for Phase II began in October 2014 with design revisions to the TxDOT 2006 SH 249 Schematic. As in Phase I, DCCM was the PMC for the design of four-lane toll lanes in each direction, adding three-lane frontage roads on both north- and southbound approaches, five major bridges, flood-mitigating storm sewer detention, a collegiate practice field, and equestrian and bike trails. Services also included computing cut-and-fill quantities for roadway sections, concrete and reinforcement steel quantities for bridge deck pours, and payments for such pours on the contractor’s pay estimate. DCCM monitored the roadway excavation, subgrade preparation, concrete milling, embankment placement for abutments, installation of drill shaft and foundations, concrete beam placement, asphalt pavement placement, bent footings, column, cap pours, reinforced earth walls, 18- to 36-inch reinforced concrete pipes, and various concrete box culverts. Our team oversaw construction management and inspection services for this segment of the project.  Phases I and II of the SH 249 (Tomball Tollway) project included environmental investigations and permitting, survey/ROW mapping, utility identification and assessment, subsurface utility engineering (SUE), and hydrologic and hydraulic (H&H) modeling and detention pond design. DCCM also provided construction phase services for Phase II and the direct connectors at SH 99 (Grand Parkway). Mainlanes, Phase I, Section 1 – Montgomery County MCTRA selected DCCM to prepare PS&E for mainlane and ramp construction for a 0.4-mile section of tollway north of Tomball, Texas. The project scope included roadway geometric design, traffic control plans, removal plans, drainage plans with both open and closed systems, SWPPP, cross-sections, general notes, specifications, and construction cost estimates. The DCCM team coordinated with both adjacent designers on the Montgomery County segment and with the design and construction teams of the Harris County segment to the south to deliver a synchronized product that minimized impacts to travelers and adjacent property owners and reduced overall project costs. At a Glance $101 million Phase I Construction Cost $99 million Phase II Construction Cost Markets Transportation Services Transportation Utilities Surveying Water & Wastewater

Scroll to Top