Portfolio

SH 249 (Tomball Tollway), Phases I and II

SH 249 (Tomball Tollway), Phases I and II Tomball and Montgomery County, Texas DCCM was contracted by the Harris County Toll Road Authority (HCTRA) as the Program Management Consultant (PMC) for the design and management of both preliminary and final project designs, as well as construction management and inspection services for Phase II. We developed a project feasibility assessment, which resulted in the SH 249 (Tomball Tollway), Phases I and II engineering feasibility report, and served as the basis for the final design. On its first day of operation, eager toll users doubled the projected 17,000 daily toll transactions, cutting traffic on the existing frontage road in half. Funded entirely with toll road revenue paid by drivers who choose to use the Harris County toll road system, the final construction will extend the toll road into Montgomery and Grimes Counties to SH 105, streamlining trips to and from rapidly growing Grimes County and College Station. Phase I: Spring Cypress Road to FM 2920 This project provided travelers with four main lanes in each direction and was constructed between the existing TxDOT northbound and southbound non-tolled frontage roads. As PMC for HCTRA, DCCM completed an aggressive 9-month design program to deliver plans, specifications, and estimates (PS&E) for HCTRA to bid and construct this phase. DCCM provided leadership, schedule adherence, quality assurance, and oversight to 17 consultants, completing the PS&E for four new toll lanes in each direction along a 6-mile stretch of SH 249, adding five new bridges, retaining walls, and a drainage system that mitigates flooding. Drivers may now bypass seven stoplights while the frontage roads remain toll-free. All milestone submittals were met on time, and the project was constructed in only 16 months and under three construction contracts. Phase I was open to traffic in April 2015 and is exceeding all revenue forecasts.  Phase II: FM 2920 to Spring Creek (Harris/Montgomery County line) Design preparations for Phase II began in October 2014 with design revisions to the TxDOT 2006 SH 249 Schematic. As in Phase I, DCCM was the PMC for the design of four-lane toll lanes in each direction, adding three-lane frontage roads on both north- and southbound approaches, five major bridges, flood-mitigating storm sewer detention, a collegiate practice field, and equestrian and bike trails. Services also included computing cut-and-fill quantities for roadway sections, concrete and reinforcement steel quantities for bridge deck pours, and payments for such pours on the contractor’s pay estimate. DCCM monitored the roadway excavation, subgrade preparation, concrete milling, embankment placement for abutments, installation of drill shaft and foundations, concrete beam placement, asphalt pavement placement, bent footings, column, cap pours, reinforced earth walls, 18- to 36-inch reinforced concrete pipes, and various concrete box culverts. Our team oversaw construction management and inspection services for this segment of the project.  Phases I and II of the SH 249 (Tomball Tollway) project included environmental investigations and permitting, survey/ROW mapping, utility identification and assessment, subsurface utility engineering, and hydrologic and hydraulic modeling and detention pond design. DCCM also provided construction phase services for Phase II and the direct connectors at SH 99 (Grand Parkway). Mainlanes, Phase I, Section 1 – Montgomery County MCTRA selected DCCM to prepare PS&E for mainlane and ramp construction for a 0.4-mile section of tollway north of Tomball, Texas. The project scope included roadway geometric design, traffic control plans, removal plans, drainage plans with both open and closed systems, SWPPP, cross-sections, general notes, specifications, and construction cost estimates. The DCCM team coordinated with both adjacent designers on the Montgomery County segment and with the design and construction teams of the Harris County segment to the south to deliver a synchronized product that minimized impacts to travelers and adjacent property owners and reduced overall project costs. At a Glance $101 million Phase I Construction Cost $99 million Phase II Construction Cost Markets Transportation Services Transportation Utilities Surveying Water & Wastewater

West Terre Haute Trail

West Terre Haute Trail West Terre Haute, IN This one-mile-long pedestrian trail is located along the south side of US 150 in West Terre Haute, beginning at Sumner Avenue and extending east to Schley Place. The goal of this project was to improve pedestrian safety, increase connectivity, reduce congestion, and improve air quality.  Prior to construction, pedestrians were forced to walk along the narrow US 150 shoulder beside traffic or behind the guardrail adjacent to the steep side slope, creating a dangerous and restricted walking path. With this project, West Terre Haute was able to provide an alternate route for commuting individuals, families, and those needing to access jobs without vehicles. This trail and bridge improved safety for pedestrians and vehicular travelers amidst increased US 150 traffic.  At a Glance 1 Mile Project Size $6.6M Project Cost ACEC State Finalist Project Award Markets Transportation Environmental Services Transportation Environmental Structural Engineering

Brays Bayou Federal Flood Control, Multiple Channel Improvements, and Bridge Replacements

Brays Bayou Federal Flood Control, Multiple Channel Improvements, and Bridge Replacements Houston, Texas DCCM was contracted by HCFCD to provide engineering services for three separate projects for Brays Bayou. Channel Modifications, Discrete Segment 109 – DCCM evaluated the impact of the proposed channel widening on the existing foundation of eight bridges. DCCM also designed soil-nail and gravity retaining walls to protect the bridge abutments and to stabilize the bayou banks. Additional services included preparing a structural analysis of the proposed walls per HCFCD criteria, PS&E, force mains relocation design, relocation and replacement of existing storm sewer flap gate boxes, and an updated evaluation of the previous IH 610 bridge engineering report. Services also included an alternative final design, evaluation of existing bridge foundations’ capacity, and a recommendation on soil excavation impact.  Telephone Road, Lawndale Street, South 75th Street, and Almeda Road Bridge Replacements – DCCM provided preliminary and final design and bid and construction phase services for the replacement of the four bridges. DCCM investigated the site, reviewed record drawings and existing utilities, and conducted a topographic survey of the existing channel and bridges to supplement the data. DCCM assisted with the coordination of lane configurations and sidewalk widths to determine typical bridge sections and prepared exhibits showing alternatives for each bridge. DCCM prepared TCPs, local drainage design, SWPPP, a drainage area map, hydraulic calculations, and drainage standards.  Stella Link Road and Ardmore Street Bridge Replacements – DCCM provided the design, coordination, scheduling, and PS&E for the replacement of the existing Ardmore Street bridge and addition of a new span to the Stella Link Road bridge. The project increased the hydraulic capacity of Brays Bayou by expanding the cross-sectional area under the bridges. The new bridge at Ardmore Street provided a U-turn, wider lanes, and sidewalks for community connectivity. The project included a compressed schedule to meet federal funding requirements, environmental issues, and utility coordination due to gas lines, storm sewer, gravity and force main sanitary sewers, and electrical and water lines on the bridges.  At a Glance $11 million Discrete Segment 109 Construction Cost $23 million Telephone Road, Lawndale Street, South 75th Street, and Almeda Road Bridge Replacements Construction Cost $23 million Stella Link Road and Ardmore Street Bridge Replacements Construction Cost Markets Transportation Services Transportation

US 59 South Reconstruction

US 59 South Reconstruction Rosenberg, Texas DCCM provided construction management, utility coordination, and roadway/utility inspection services for the construction and inspection of US 59 South from west of SH 762 to west of FM 2759 in Richmond. The transformation of the roadway included widening US 59 from a four-lane rural freeway to an eight-lane freeway, with two-way high-occupancy vehicle lanes and improved frontage roads. Also included in this project were upgrades to grading, cement-treated base, concrete pavement, a computerized transportation management system, bridges, a storm drain, signing, pavement marking, lighting, and traffic signals. DCCM provided support for the inspection of substructures and superstructures on this project. DCCM also assigned utility inspectors to verify the proposed alignment of utility relocation and to monitor the installation of utilities, working closely with owners and assigned subcontractors to ensure that the proposed utilities were placed per the approved plan and profile. At a Glance $162 million Project Cost Markets Transportation Services Transportation

SH 249 (Tomball Tollway), Phase II and Four Direct Connectors

SH 249 (Tomball Tollway), Phase II and Four Direct Connectors Tomball, Texas DCCM performed construction engineering inspection services for the SH 249 (Tomball Tollway), Phase II, and the SH 249 (Tomball Tollway) and SH 99 (Grand Parkway) direct connectors projects. DCCM provided Field Engineers, Office Engineers, Critical Path Method, Sr. Scheduler, Construction Inspectors, and Utility Inspectors for both projects. DCCM also performed subsurface utility engineering as needed for fiber-optic cables (AT&T, Verizon), pipelines, and City of Tomball water lines. In addition, DCCM reviewed the detection of defects or deficiencies in the project contractor’s work. To support timely project completion, DCCM responded to the project request for information, coordinated and tracked submittals, reviewed and approved required project shop drawings, and provided other services requested by the Harris County Toll Road Authority. SH 249 (TOMBALL TOLLWAY), PHASE II CONSTRUCTION The project included the construction of six toll lanes and two three-lane frontage roads, including grading, embankment, drainage, structures, stormwater detention, signing, cement-treated base, stormwater pollution prevention plan, tolling infrastructure, a computerized transportation management system, and continuously reinforced concrete pavement. SH 249 (TOMBALL TOLLWAY) AND SH 99 (GRAND PARKWAY) DIRECT CONNECTORS The project included the construction of the SH 249 (Tomball Tollway) and SH 99 (Grand Parkway) four direct connectors and approaches, including traffic control, earthwork, grading, paving, structures, retaining walls, drainage, illumination, signing, pavement markings, an intelligent transportation system, and cross-sections. At a Glance $99 million Phase II $92 million Direct Connectors Markets Transportation Services Transportation

IH 45 South Expansion

IH 45 South Expansion Galveston County, Texas The expansion of IH 45 South in Galveston County was designed to widen the interstate and improve mobility in a region that has seen continuous growth in recent years. DCCM provided utility relocation and inspection (including water line, communication cable, and gas line), grading, concrete pavement, asphalt-stabilized base, cement- and lime-treated base/subgrade, bridge structures, storm sewer, and detentions. Construction of the widening of a freeway facility included grading, concrete pavement, asphalt-stabilized base, cement-treated base, lime-treated subgrade, asphalt concrete pavement, bridge structures, storm sewers, detention ponds, retaining walls, signing, pavement markings, traffic signals, continuous lighting, and a traffic management system. DCCM was selected to perform utility coordination, subsurface utility engineering, and utility inspection for the entire project. DCCM provided utility coordination and relocation for Frontier, AT&T, Comcast, CenterPoint Energy gas, Texas-New Mexico Power, and Phonoscope. DCCM performed subsurface utility engineering to identify the existing 39-inch encased water line (City of League City) that hindered the construction of the drilled shaft and stone columns along abutment No. 1 on the SH 96 bridge widening. TxDOT also entrusted DCCM with reviewing and approving permit applications for the entire project’s proposed relocation. At a Glance $101.7 million Project Cost Markets Transportation Services Transportation

Downtown Underground Transmission Duct Bank Installation

Downtown Underground Transmission Duct Bank Installation Houston, Texas DCCM provided engineering and construction support services for the design of a 138-kilovolt transmission duct bank to replace aging oil-filled facilities serving the growing, highly congested Downtown and Midtown areas of Houston. More than 12,600 linear feet of underground transmission duct back was designed to connect three critical substations that serve these areas. The design included installations within existing substation facilities along and across TxDOT right-of-way, through the St. Joseph Medical Center, in front of the Toyota Center, and under the METRORail Red Line. DCCM worked with the client to optimize the duct bank configuration and layout to maximize the efficiency of construction and operational methods. DCCM utilized specialized planning and equipment to accommodate two horizontal directional drilling rigs in very restrictive, narrow, and congested areas of the project. Professional services included engineering analysis and design, topographic survey, signed and sealed plan and profile drawings, traffic control plans, construction method solutions, conflict resolutions, utility research, coordination and permitting (with TxDOT, City of Houston, and Metropolitan Transit Authority of Harris County [METRO]), signed and sealed as-built plans, geotechnical services, and construction phase support. All designs complied with the client’s standards and specifications, as well as federal, state, and municipal requirements. At a Glance 12,600 Linear Feet $303,000 Design Cost Markets Power Services Utilities

Transmission Counterpoise along BNSF Railroad

Transmission Counterpoise along BNSF Railroad Montgomery County, Texas With growing concerns about the effects of electromagnetic fields generated by overhead electric transmission lines on the rails of tracks managed by the Burlington Northern Santa Fe (BNSF). DCCM was selected to design and coordinate with the client and BNSF for the installation of a counterpoise system to neutralize electromagnetic fields along 12 miles of paralleling tracks and a 345-kilovolt transmission line. This counterpoise system consisted of four 500 MCM buried bare copper cables along the BNSF right-of-way, two on each side, installed at strategic distances from the tracks to achieve optimal efficiency for its purpose. DCCM developed detailed construction drawings for cable installation, including horizontal directional drilling, a railroad plow, and an open trench. DCCM obtained all necessary permits from the County, TxDOT, the US Army Corps of Engineers, and BNSF. At a Glance 345 kV Transmission Line 12 Miles Railroad Markets Power Services Utilities

US 290-IH 610 Interchange Gas Relocation

US 290/IH 610 Interchange Gas Relocation Houston, Texas TxDOT is widening and reconstructing the 25-mile US 290 Corridor at an estimated cost of $4.7 billion to accommodate growth on the west and northwestern sides of Houston. The project is being completed within 13 segments, the widening includes five/six general purpose lanes in each direction from IH 610 to just west of SH 6, four general-purpose lanes in each direction from just west of SH 6 near to the proposed SH 99 (Grand Parkway), three general-purpose lanes in each direction from nearby proposed SH 99 (Grand Parkway) to the end of project, and two to three lane frontage roads in each direction throughout the corridor. DCCM was selected to install over 4 miles of polyethylene and steel pipes. The main pipe diameters ranged from 2 to 12 inches for intermediate-pressure (IP) and high-pressure (HP) lines. Designs for open cut and horizontal directional drill (HDD) methods were used, in accordance with our client’s policies and guidelines, as well as state and municipal requirements.  This project will extend the IH 10 West and IH 610 reconstruction, where DCCM provided complete utility services. We support communities by providing utility designs to deliver much-needed infrastructure relief, aiming to reduce delays and injuries for the 250,000 vehicles that travel through this intersection daily.  At a Glance 4 Miles Polyethylene and Steel Pipes $4.7B Overall Construction Cost Markets Power Services Utilities

Neighborhood Replacement Program

Neighborhood Replacement Program Various Locations, Texas DCCM provided engineering services for replacing pre-84 distribution system pipelines for a confidential client. All low-pressure and intermediate-pressure pipelines made of ductile iron or steel were replaced with IP high-density polyethylene pipelines. Replacement of pipelines was part of the natural gas distribution Integrity Management Program as established in Texas Administrative Code, Title 16, Part 1, Rule 8.209. DCCM has currently designed over 16 miles of pipeline replacements in multiple areas throughout the cities of Mart, Hillsboro, and Waco. Services for this project included permit coordination with TxDOT and the cities of Mart, Hillsboro, and Waco; plan views of proposed gas mains; replacement of residential service lines; placement of proposed valves and mainline fittings; design of connection details; estimating project quantities; and retirement of regulator stations. All designs were completed in accordance with the client’s standards and specifications, as well as with federal, state, and municipal requirements. At a Glance 16 Miles of Pipeline Replacement Confidential Project Cost Markets Power Services Utilities

Scroll to Top